Replacement Work To Begin On Stahle Run Bridge

PennDOT has announced that Fulton County residents will soon have a smoother and safer ride across the Route 3002 (Harmonia Road) Stahle Run Bridge in Union Township as superstructure replacement work will begin on Monday, June 4.

Department forces will remove the existing superstructure and a portion of the abutments, construct a new concrete abutment cap, backfill, apply a waterproof membrane to the bridge deck then place a bituminous overlay across the structure. This work is expected to take eight to 10 weeks to complete.

A signed detour will be in place that will route motorists onto Route 484 (Buck Valley Road) around the project.

Fulton County Maintenance is the contractor on this $160,000 project that is expected to be completed by August 2012.

Follow local PennDOT information on Twitter at www.twitter.com/511PAAltoona.